Renewable Energy Zones: the plan and the pushback

29 November 2026 · by Anjali Rao
8 min read·1756 words·Updated 29 Nov 2026

Nine. That’s roughly how many formally declared Renewable Energy Zones now sit across the National Electricity Market, spread from the Queensland border down through NSW, Victoria and South Australia. On paper it’s the neatest idea in the Integrated System Plan: pick the best wind and solar resource, build the transmission to match, let generators queue up for a known slice of capacity instead of fighting each other for a connection point nobody planned for. In practice I’ve spent a fair chunk of this year on the phone to landholders, developers and a couple of transmission planners who’d rather not be named, and the gap between the zone on AEMO’s map and the zone on the ground has become the main story of the transition.

Let’s start with what a REZ actually is, because the term gets thrown around loosely enough that I reckon half the people using it in a press release couldn’t define it. A Renewable Energy Zone is a geographic area identified by AEMO and the relevant state government as having strong wind or solar resource, where new shared transmission infrastructure is built ahead of (or alongside) generation, with access rights allocated through a competitive process rather than first-come-first-served. The logic is sound engineering: build one big line instead of a dozen generators each building their own spur to the nearest substation. The problem is that “build one big line” turns out to be the hardest sentence in the entire document.

The original pitch and why it made sense

Go back to the 2020 Integrated System Plan and the REZ concept was sold as a cost-sharing mechanism as much as a planning one. Instead of every wind or solar developer paying for their own connection, and passing that cost through in their power purchase agreements: the REZ spreads transmission cost across everyone who connects, with the network business recovering it through regulated revenue. AEMO’s most recent Integrated System Plan still treats REZ build-out as the backbone of the optimal development path to 2050, and I don’t think that assumption is wrong. Coordinated transmission genuinely is cheaper than piecemeal spurs, and the zones were drawn against real wind and solar resource data, not politics. I’ve written before about what the ISP actually says versus what gets quoted from it, and the REZ concept survives that scrutiny better than most of the document’s more optimistic timelines.

Where it gets harder is in the gap between declaring a zone and energising the wires inside it. Central-West Orana in NSW was meant to be the proof of concept – first zone declared, generators queued early, transmission meant to follow. It’s still, by most honest accounts, half-wired, with the backbone transmission running years behind the generation that signed up for it. New England REZ, further north, has the same shape: a long queue of proponents and a transmission timeline that keeps moving right. I covered both of those in more detail elsewhere, and the pattern repeats enough that it’s no longer an isolated hiccup. It’s the default experience of being an early mover in a REZ.

Who actually builds the wires, and on whose schedule

This is where the REZ model runs into a genuine structural mismatch. The zone is declared by the state and endorsed through the ISP process. The transmission inside it is built by the incumbent network business (Transgrid in NSW, AusNet or Victorian equivalents in Victoria, Powerlink in Queensland) under the normal regulatory investment test, with the AER setting the allowed revenue. That’s a sensible cost-recovery mechanism for a distribution upgrade. It’s a much clumsier fit for a multi-billion-dollar transmission corridor that has to go through landholder negotiation, environmental approval and, increasingly, legal challenge, all before a single tower goes up.

HumeLink is the clearest illustration of what happens when that mismatch bites. The project’s capital cost has nearly tripled from its original estimate, and a meaningful share of the blowout traces directly to landholder negotiation and undergrounding demands rather than steel and conductor costs. Transgrid, which is building it, has been candid in its own regulatory filings that cost escalation on transmission easements has outpaced almost every other input. I don’t think that’s a reason to abandon REZ transmission as a concept, but it is a reason to stop quoting REZ cost estimates as if they were fixed numbers. AEMO’s own ISP revises its transmission cost assumptions with almost every update, and anyone citing a REZ build cost from more than eighteen months ago is probably already out of date.

The landholder pushback is not a PR problem

I’ve heard REZ transmission routes described by state energy departments as a communications challenge – get the community consultation right and the opposition softens. Having sat in on a couple of those consultations, I think that framing understates what’s actually going on. Landholders along proposed REZ corridors are being asked to host permanent easements for infrastructure that benefits a grid, not necessarily their own property, and the compensation frameworks vary by state and by network business in ways that genuinely confuse people. Some are offered one-off payments; some states, including NSW, have moved toward annual payments for landholders hosting transmission infrastructure, which is a reasonable policy response but one that arrived well after the first wave of REZ routes was already being surveyed.

The undergrounding debate sits inside this same argument. Undergrounding transmission costs several times more than an overhead line of equivalent capacity: the multiple depends on terrain and voltage, but it’s not a marginal difference, it’s a different order of project. When a community group demands undergrounding as the price of social licence, that’s not an unreasonable ask on its own terms, but it changes the cost-benefit maths of the entire zone. Worth being honest that the REZ model, as designed, didn’t really budget for that negotiation at scale. It assumed overhead lines along efficient corridors and treated landholder engagement as a process step rather than a cost driver. Reality has corrected that assumption, expensively.

A full queue is not the same as a working zone

Here’s the distinction I keep coming back to with readers who ask why a REZ with a long connection queue still has blackspots in supply. Queue position tells you how many megawatts of generation want to connect. It tells you nothing about whether the shared transmission exists to actually move that power to load. New England REZ has exactly this profile: a healthy pipeline of wind and solar proponents, a connection process that’s progressed, and a transmission backbone that is, as I’ve reported before, still catching up. A wind farm fully built and sitting behind a transmission bottleneck doesn’t generate revenue; it generates curtailment, and curtailment is dead weight on a developer’s return model regardless of how good the wind resource measured on the met mast.

Worked example, roughly: say a REZ has 3,000 megawatts of generation capacity queued and connected, but the shared transmission into the zone can only firmly carry 1,800 megawatts of power at any one time. On a strong wind day, that’s 1,200 megawatts of capacity either curtailed or constrained, not necessarily simultaneously, and not every day, but often enough that the zone’s effective utilisation sits well under its nameplate. That’s the mechanical reality behind every “REZ delayed” headline, and it’s also why big batteries have become part of the REZ conversation, not just for arbitrage, but as a way to soak up power the transmission can’t move in real time and release it later. Whether batteries are actually being built for that job, versus the market-arbitrage job they’re more commonly optimised for, is a separate argument I’ve made elsewhere and won’t repeat here.

The zones aren’t uniform, and the targets behind them aren’t either

One thing that gets lost in national coverage of REZs is how differently each state has structured its target and its funding model. Victoria’s REZ work sits inside a broader state renewable target that’s more aggressive on timeline than the national trajectory; Queensland’s zones are tangled up with a public-ownership pumped hydro bet that shapes which REZ corridors get prioritised for transmission funding. NSW runs its own REZ investment vehicle through its energy infrastructure roadmap, with access rights auctioned competitively. Comparing state renewable targets honestly means admitting they’re not measuring the same thing with the same enforcement mechanism, and REZ delivery timelines inherit that inconsistency.

Western Australia’s isolated grid doesn’t really run REZs in the NEM sense at all, which is its own instructive comparison: a grid with no interconnector to lean on has had to solve firming and zone planning through a completely different regulatory path, and it’s worth a look if you want to see what REZ planning looks like without the coordination (and squabbling) that comes from sharing a market with four other states.

What actually tells you whether a REZ is working

If I were scoring REZ progress for a reader with one number, I wouldn’t use the declared megawatts of generation in the queue. I’d use the ratio of energised transmission capacity to queued generation capacity, tracked over time, zone by zone. That number is harder to find: AEMO publishes connection and transmission progress in its planning reports, but you have to dig, and the AEMC’s transmission access reform work is the other place worth checking for how access rights are actually being allocated once a line is built. The gap between “declared” and “energised” is where almost every REZ story I’ve filed this year has actually lived, and I don’t expect that to change quickly. Transmission build timelines are measured in years per project even when nothing goes wrong, and on the current run of projects, something has gone wrong fairly often.

None of this means the REZ model should be abandoned – coordinated transmission still beats the alternative of a dozen uncoordinated spur lines fighting for the same substation capacity, and I’d rather argue about cost overruns on a sound plan than watch generators build connection infrastructure with no shared strategy at all. But the public conversation around REZs has been sold on queue numbers and declared-zone maps for long enough. The wires are the actual deliverable, and on most of the zones I’ve tracked this year, the wires are still the thing running behind schedule. Next time a minister announces a new REZ, I’d want to know the energisation date for the backbone transmission before I’d get excited about the gigawatts queued behind it: a bit like judging a chess position by the pieces on the board rather than whose move it actually is.

– Anjali Rao, Grid & Storage Correspondent