Will Snowy 2.0 ever earn its keep?

27 November 2026 · by Marcus Wren
7 min read·1543 words·Updated 27 Nov 2026

$12 billion. That’s roughly where the public capital estimate for Snowy 2.0 now sits, more than three times the figure floated when the project was announced back in 2017. Tunnel boring has been plagued by geology nobody fully modelled, the in-service date has slipped past 2028 for the main caverns, and the scheme still hasn’t delivered a single megawatt of its promised 2,000 MW, eight-hour storage capacity. So it’s a fair question, and not a cheap shot: will this thing ever actually pay for itself?

I don’t think the answer is a clean yes or no. It’s more uncomfortable than that.

The case the original business plan made #

Snowy Hydro’s own case, laid out when the scheme was approved, rested on arbitrage. Pump water uphill using cheap, often negative-priced midday solar power, release it through turbines during evening peaks when prices spike, and pocket the spread. That’s a sound mechanism in principle. It’s the same logic behind every battery and every pumped hydro scheme anywhere in the world. The trouble is the spread Snowy 2.0 needs to recover a $12 billion build is a lot wider than the spread that existed when the number on the table was $2 billion.

Follow the money and the arithmetic gets harder, not easier, the longer construction drags on. Every year of delay is a year of forgone revenue plus financing cost on capital that’s already sunk into tunnels under Kosciuszko National Park. Snowy Hydro is a Commonwealth-owned entity, so there’s no share price punishing this in real time the way the market would for a listed gentailer. That’s precisely why it deserves more scrutiny, not less – nobody’s forcing the discipline that comes from a quarterly result.

What’s changed in the market since the business case was written #

Here’s the structural problem. When Snowy 2.0 was conceived, big batteries barely existed in the NEM. Now they’re everywhere, and they do a chunk of the job Snowy 2.0 was built to do – soaking up midday solar, discharging into the evening peak – at a fraction of the capital cost and on a construction timeline measured in months, not a decade. I’ve written before about whether big batteries are being built for the wrong job, and the honest read is that most of the fleet currently operating is two hours of storage, not eight. That’s actually Snowy 2.0’s one genuine point of difference: duration. A battery that runs flat after two hours can’t carry a grid through a multi-day wind lull. Pumped hydro with eight hours of discharge can, at least partially.

But duration only matters commercially if the price spread during those long events is wide enough, and wide enough often, to recover the capital. AEMO’s own Integrated System Plan models a system that increasingly needs long-duration firming as coal exits. I went through what that document actually commits to in this piece on the ISP, but modelled need and bankable revenue aren’t the same thing. The ISP can say the system needs 15 gigawatts of long-duration storage by the mid-2030s. It can’t guarantee the market pays Snowy Hydro a return that justifies $12 billion of sunk tunnel.

The negative-price problem cuts both ways #

There’s a wrinkle that gets missed in a lot of the commentary defending the project. Negative prices at midday, the very condition Snowy 2.0 is meant to exploit for cheap pumping, are becoming so frequent and so deep that they’re reshaping the whole merit order. I’ve covered what negative prices at midday actually mean for the grid, and the short version is: rooftop solar alone is now routinely pushing wholesale prices below zero across multiple states, for hours at a stretch, well before Snowy 2.0 is even online.

That sounds like good news for a pumped hydro scheme designed to buy cheap and sell dear. It mostly is. But it also means every other big battery, every other pumped hydro scheme, and increasingly demand-response and EV charging are competing for exactly the same cheap midday window to fill up. The arbitrage opportunity doesn’t belong to Snowy 2.0 alone. By the time the scheme is actually generating revenue, it’ll be fighting for margin against a storage fleet that’s grown enormously in the interim, including Queensland’s own pumped hydro ambitions at Borumba and the Waratah Super Battery already doing grid-stability work in NSW today.

Geology doesn’t care about your spreadsheet #

I’ll admit the tunnelling saga still catches me by surprise each time a new delay surfaces. Florence, the tunnel boring machine that became almost a mascot for this project’s troubles, got stuck multiple times in difficult rock conditions well below the Snowy Mountains, and each stoppage has added months and dollars that weren’t in anybody’s original model. This isn’t a dig at the engineers on site; hard rock tunnelling at that scale, under a national park, with environmental conditions attached under state planning approvals, was always going to carry risk that a Powerpoint business case can’t fully price. But risk that materialises still has to be paid for by someone, and in this case that someone is the Commonwealth balance sheet, which means taxpayers, directly or through Snowy Hydro’s own borrowing.

Snowy Hydro’s own annual reports and ASX-adjacent disclosures (as a Commonwealth corporation it reports through different channels than a listed company, but the project updates are public) have tracked the capital estimate rising in stages: from the original $2 billion, to $3.8 billion, then past $5 billion, and now sitting around the $12 billion mark with some commentary suggesting further cost pressure isn’t finished. That’s not a scandal. Big tunnelling projects blow out; HumeLink’s transmission cost has done something similar, and I’ve covered that blowout in detail. What matters for Snowy 2.0 specifically is whether the revenue side of the ledger can ever catch up to a capital figure that’s grown sixfold.

Who actually captures the value #

Here’s where I land, and I’ll own that it’s a view rather than a certainty. Snowy 2.0 will almost certainly deliver real grid value once it’s finished – long-duration firming is genuinely useful, arguably more useful with each additional gigawatt of variable renewable generation that comes online. The question was never whether the asset does something. It’s whether the something it does is worth what’s been spent building it, measured against the alternatives that exist now but didn’t exist when the project was approved.

My honest read is that Snowy 2.0 will operate for decades, provide meaningful system security, and never generate a commercial return that would justify a private developer making the same bet at today’s capital cost. That’s not a reason to abandon it: the tunnels are mostly dug, the turbines are mostly ordered, and walking away now would waste more than finishing does. It is a reason to stop pretending the project’s economics are comparable to a battery or a wind farm assessed on a standard payback basis. This is closer to the way we should think about public versus private ownership of generation more broadly – some assets get built because the system needs the insurance, not because the spreadsheet clears.

The comparison nobody wants to make out loud #

Put Snowy 2.0 next to Tasmania’s Battery of the Nation ambitions, which I’ve written about before, and the contrast is instructive. Tasmania’s whole pitch rests on one cable, Marinus Link, actually getting built and actually carrying the volumes modelled. Snowy 2.0’s pitch rests on tunnels that are already dug needing to earn a return nobody budgeted for at this scale. Both are examples of nation-building infrastructure where the case for building it and the case for it paying its way have quietly become two separate arguments. Governments are comfortable making the first argument. They’re a lot less comfortable being pinned down on the second.

The Australian Energy Market Operator’s published ISP documents are a reasonable public reference for the system-level need case, and anyone wanting the primary source rather than my summary of it should read AEMO’s own material directly at aemo.com.au. For the project’s own cost disclosures, Snowy Hydro’s corporate updates sit on its public site, and the Department of Climate Change, Energy, the Environment and Water’s portfolio reporting also tracks Commonwealth exposure to the project over time, available through the department’s own publications at dcceew.gov.au.

What would change my mind #

I’d shift this view if two things happened. First, if the remaining construction schedule actually holds from here, with no further major cost revisions, because a chunk of my scepticism is really scepticism about the forecasting track record rather than the engineering itself. Second, if wholesale price volatility in the evening peak widens meaningfully as coal exits accelerate, not the midday trough, which is getting crowded, but the evening spread that an eight-hour discharge asset is actually built to capture. If that spread opens up the way some of AEMO’s more stressed scenarios suggest it could, Snowy 2.0’s economics look a lot less ugly than the capital number alone suggests.

Until then, I’d treat anyone who tells you with confidence that Snowy 2.0 is either a disaster or a triumph with some caution. It’s neither, yet. It’s a very expensive insurance policy that we’ve already bought and are still waiting to find out the premium on. The honest read is that we’ll know a lot more in 2029 than we do now, and anyone pretending otherwise is reading a spreadsheet, not the mountain.

– Marcus Wren, Editor