Loy Yang A’s owner put a number on the table earlier this year that didn’t get the attention it deserved: AGL’s own planning assumes the plant runs into the early 2030s, not much beyond it. Pair that with Eraring’s extension to 2027 and Yallourn’s confirmed exit in 2028, and you’ve got three of the NEM’s biggest coal units all heading for the door inside roughly the same decade. The argument about whether that’s reckless or overdue has been running since at least the Hazelwood closure in 2017, and it still hasn’t been settled, because the two camps are measuring different things and calling it the same argument.
Agree on the units first. Reliability, in AEMO’s own framework, is measured against the Interim Reliability Standard: the expected unserved energy must stay under 0.002% of demand in a region in a year. That’s not a vibe, it’s a number with a numerator and a denominator, and most of the public fight about coal closures never gets anywhere near it. People argue about vibes – “the lights will go out” versus “renewables are ready” – when the actual document that’s supposed to settle this, the AEMO Electricity Statement of Opportunities, publishes a USE forecast every year that either breaches that standard in the outlook period or it doesn’t.
What the ESOO has actually flagged #
The last several editions have flagged reliability gaps in Victoria and New South Wales in the back half of this decade, mostly tied to the timing mismatch between confirmed coal retirements and the firmed renewable capacity meant to replace them. That’s not alarmism, it’s the forecasting process doing its job: flag a gap, and the market and the regulator respond with things like the NSW Energy Security Target and the Capacity Investment Scheme tenders. The gap AEMO has flagged has narrowed in some years and widened in others as projects slip. The point I’d make to anyone treating the ESOO as either a doomsday clock or a reassurance blanket is that it’s neither. It’s a probabilistic forecast that gets revised, and the revisions matter more than the headline number from any single year.
I’ve gone back through four years of ESOO editions for this piece, mostly because I don’t trust my own memory of which year said what, and the pattern is consistent: the near-term years (one to two years out) are usually fine, the medium-term years (three to five out) are where the amber flags show up, and the long-term outlook depends entirely on build rates that haven’t yet been tested at the scale assumed in the Integrated System Plan. That’s a structural feature of any forecasting exercise built on projects that are announced but not built, not evidence of anyone cooking the numbers.
The closures that are actually locked in #
Eraring’s case is instructive because it’s the deal everyone cites and almost nobody describes accurately. Origin didn’t walk away from its original 2025 closure date because the maths changed in its favour: the NSW government paid for the extension, structured as a deal that keeps the plant running to 2027 with a risk-sharing and potential payment arrangement if the plant loses money in that window. I’ve written before about what that deal actually bought NSW, and the short version is two more winters of headroom, not a reprieve from the underlying retirement decision. Yallourn’s 2028 date, similarly, isn’t a threat or a projection. It’s in EnergyAustralia’s own public statements and it hasn’t moved. Loy Yang A’s timing is softer, an assumption rather than a locked date, which is exactly where the uncertainty in this debate actually lives.
The useful distinction the public argument keeps missing is between confirmed retirements with dates attached and assumed retirements based on asset age and economics. Treating them with equal weight is how you get headlines that overstate the imminent risk, and also how you get complacency about plants that genuinely are approaching end of technical life whether or not anyone’s announced it formally.
What’s meant to replace the gap #
The replacement side of the ledger is batteries, firmed renewables and transmission, roughly in that order of what’s actually been built versus what’s been approved. The Waratah Super Battery is doing real work as a grid stabiliser in NSW, and the fleet of big batteries coming online across the NEM is genuinely useful for the fast, short-duration problem – frequency response, the five-minute dispatch intervals AEMO manages constantly. What batteries at current scale don’t yet do is cover the multi-day, low-wind, low-sun stretch that a coal unit running at high capacity factor used to cover almost by default. I wrote a while back about why most big batteries on the system today are built around a two-hour discharge window, and that duration question doesn’t disappear just because the headline megawatt figure sounds impressive.
Transmission is the other half of the replacement story and it’s the half that’s running late almost everywhere. HumeLink’s cost blowout and the New England REZ’s wires-behind-generation problem are both symptoms of the same thing: renewable energy zones get projects connected to a queue faster than the poles and wires get built to shift that power to where coal used to supply it from. You can have confirmed closure dates and confirmed replacement projects and still have a reliability gap if the transmission between them isn’t finished on time. That’s the mechanical reality the public debate mostly skips past in favour of arguing about whether coal or renewables are “to blame,” which isn’t really the right question.
Where gas still sits in this #
Gas peakers are the bridge technology everyone name-checks and almost nobody wants to pay for at the capacity needed. Kurri Kurri finally got built after a long and public argument about its economics, and I think that saga is a reasonable preview of what’s coming for every other peaker proposal in the queue: long lead times, cost overruns relative to original announcements, and a finished asset that then sits mostly idle, earning its money in the hours when everything else falls short. That’s not a criticism of the technology, it’s just what peaking plant economics look like, and it’s worth being honest about rather than pretending gas peakers are either villains or saviours.
The debate over whether gas peakers or big batteries win the firming job isn’t actually an either/or, and I covered that ground in more detail recently: the honest answer is that they do different jobs on different timescales, and the system increasingly needs both rather than a clean substitute for either.
The capacity factor trap #
Here’s where I think the public argument goes wrong most often, and it’s a mild gripe of mine that’s come up before: people compare nameplate megawatts of closing coal against nameplate megawatts of new renewables and call it even, when the two numbers aren’t doing the same work. A coal unit running at a high capacity factor delivers energy on a completely different reliability profile to a wind or solar project running at a third of that, however large its nameplate. I went through the actual maths on this a while back under the heading of capacity factor, and it’s the single most under-appreciated number in this whole fight. Reliability planning has to account for that gap explicitly, which is exactly what the ESOO tries to do, with varying success depending how optimistic the build-rate assumptions are in any given year.
My own read on the timing #
If you push me for a verdict rather than a description of the forecasting, I’d say the closures themselves are mostly fine – plants built in the 1970s and 80s don’t get safer or cheaper to run by delaying the decision, and the Hazelwood precedent showed the market can absorb a sudden exit without the system collapsing. The actual risk isn’t the closures, it’s the build rate for transmission specifically. Batteries are turning up roughly on schedule. Transmission consistently isn’t, and HumeLink is the clearest illustration of why: a project whose capital cost estimate has moved from the low billions to nearly five, with a timeline that’s slipped more than once. If I had one genuine worry for the next five years of ESOO editions, it wouldn’t be coal exit dates. It’d be whether the wires get finished before the coal units they’re meant to replace actually switch off.
There’s also a quieter argument that doesn’t get made often enough: some of the states managing this best, South Australia in particular, did it by accepting a higher tolerance for short-term price volatility in exchange for faster renewable build. The SA experience suggests the reliability debate might be less about any single technology and more about how much short-term pain a market and its political system are willing to absorb for a faster transition. NSW and Victoria, so far, have chosen a slower, more cushioned path, which costs more in extension payments and government intervention but buys more certainty. Neither approach is obviously wrong. They’re just different bets on the same underlying maths.
Worth watching, over the next couple of ESOO cycles, whether the medium-term amber flags start clearing as the REZ transmission backlog actually gets built, or whether they just keep moving three years further out every year, the way a looming deadline sometimes does when nobody wants to be the one who missed it.
– Tom Fitzgerald, Baseload & Fuels Correspondent