Fossil Fuels & Gas

Small modular reactors: what the technology can actually do now

28 November 2026 · by Tom Fitzgerald
7 min read·1582 words·Updated 28 Nov 2026

NuScale’s US-240 design got through the Nuclear Regulatory Commission’s final safety evaluation back in 2023. Three years on, there is still no operating small modular reactor selling power into any grid that looks remotely like the NEM. That gap between “approved on paper” and “running and dispatchable” is the whole story of this technology, and it’s the bit that gets lost whenever the subject comes up at a dinner party in Perth or a Senate estimates hearing in Canberra.

I’ve had this argument more times this year than I can count, usually starting from someone quoting a brochure capacity figure as if it were a commissioned asset. So let’s agree on the units first, because the units are where most of the confusion lives.

What “small” and “modular” actually mean #

A small modular reactor, in the industry’s own definition, is anything up to roughly 300 megawatts of electrical output, built from factory-fabricated modules rather than poured and welded entirely on site. The “modular” part is the genuinely interesting bit: the pitch is that you build reactor vessels and major components in a factory, truck or ship them to site, and assemble rather than construct. That’s supposed to turn nuclear from a bespoke civil-engineering megaproject into something closer to a manufactured product, with the cost curve that implies – falling unit costs as you build the tenth one instead of the first.

It’s a reasonable theory. It’s also, as of November 2026, a theory still waiting on its first proof point at scale. NuScale cancelled its flagship Utah customer project (the Carbon Free Power Project with Utah Associated Municipal Power Systems) in 2023 after costs blew out and subscriber utilities pulled back. The company has since pivoted toward international and data-centre customers, but the US still doesn’t have a commercial SMR generating revenue power. China’s HTR-PM, a high-temperature gas-cooled demonstration unit at Shidao Bay, did enter commercial operation in 2023. That’s the one genuine, in-service small modular plant anywhere in the world right now, and it’s worth being precise that it is one unit of around 200 megawatts, not a fleet.

Russia’s floating plant and the “it already works” argument #

People who want to wave away the scepticism usually point to Russia’s Akademik Lomonosov, a floating nuclear plant moored off Pevek in the Russian Far East since 2020, using two 35-megawatt KLT-40S reactors adapted from icebreaker propulsion units. It’s real, it’s running, and it does supply a remote grid. But it’s also a one-off built by a state nuclear monopoly for a strategic Arctic outpost, derived from decades of naval reactor experience that doesn’t transfer cleanly to a civilian competitive market with an independent regulator and a wholesale price that moves every five minutes. Pointing to Pevek as proof the SMR market has arrived is a bit like pointing to a Formula One pit crew’s tyre change time and concluding your local Supercheap Auto can do your brakes in four seconds.

Where the actual projects sit today #

Strip away the slide decks and there are perhaps half a dozen designs anywhere close to a real construction decision. GE Hitachi’s BWRX-300 is probably furthest along outside China and Russia: Ontario Power Generation broke ground on one at Darlington, with a targeted in-service date later this decade, and TVA in the US has signed on for its own unit. Rolls-Royce’s SMR design is working through UK regulatory assessment with a first unit targeted for the early 2030s. X-energy’s Xe-100, backed partly by Amazon’s own money for data-centre power, is working toward a Texas demonstration. Holtec, Terrapower, Kairos – all real companies with real engineering teams and real money behind them, and all still pre-construction or in early-stage builds measured in years, not months.

None of that is a knock on the engineering. It’s a statement about where the technology sits on the maturity curve, which is roughly where offshore wind sat in the mid-2000s: credible, backed by serious capital, and a decade or more from being a boring commodity purchase decision. The AEMO Integrated System Plan doesn’t include SMRs in its optimal development path for the National Electricity Market, and that’s not AEMO being ideological about it. It’s AEMO looking at cost, schedule and the existing moratorium on nuclear generation in Commonwealth and most state legislation and concluding there’s nothing bankable to model yet. I wrote about what that plan actually assumes in what the AEMO Integrated System Plan actually says, and the SMR gap in it is conspicuous precisely because the plan is otherwise quite generous to every firming technology going.

The economics nobody wants to sit with #

The modular promise was supposed to be learning-curve economics: factory repetition drives the cost per unit down, the way it did for solar panels and lithium cells. The uncomfortable bit is that nuclear hasn’t behaved that way historically, even at full reactor scale – costs have tended to rise with experience in Western markets, not fall, largely because safety case requirements, site-specific civil works and regulatory review have grown heavier each cycle rather than lighter. NuScale’s own cost estimate for the Utah project rose substantially between its original 2020 projection and the 2023 cancellation, and that was before a single module had been poured. Whether SMRs break that pattern or repeat it is genuinely unresolved, and I’d treat anyone who states it with confidence either way as selling something.

For Australia specifically, there’s a second layer: no SMR design has completed assessment or licensing anywhere near our domestic framework, there’s no local fuel cycle or waste pathway established, and the federal moratorium under the Australian Radiation Protection and Nuclear Safety Act would need to be repealed before a civilian plant could be licensed at all, on top of whatever each state does with its own prohibition. I went through the cost and timeline maths on the Coalition’s broader nuclear proposal in the Coalition’s nuclear plan: the cost and timeline maths, and the SMR variant of that argument runs into the same wall a few years earlier in the schedule, not later – smaller units in theory build faster, but “in theory” is doing a lot of work when nobody has built a fleet of them yet to compare against.

What SMRs are actually good at, on the numbers that exist #

None of this means the technology is worthless, and it’s worth being fair to it. Where SMRs look genuinely sensible, on the evidence that does exist, is remote or islanded load with no cheap renewable-plus-storage alternative – think isolated mining operations, data centres wanting firm baseload without a grid connection, or small island grids like the one Russia built Pevek for. That’s a different job to replacing a retiring coal unit on the NEM, where capacity factor and dispatch flexibility matter as much as raw output, and where a battery plus gas peaker combination is already commercially available today rather than theoretically available sometime in the 2030s. I’ve made the case elsewhere that batteries get built for the wrong job as often as the right one – see are big batteries being built for the wrong job?, and the honest comparison with SMRs is that at least batteries are actually being built, at scale, right now, with known costs. SMRs are being planned, at scale, eventually, with costs that are still estimates.

The regulatory clock nobody talks about #

Here’s the part that tends to get skipped in the political version of this debate: even in jurisdictions that want SMRs and have no legislative prohibition, the regulatory assessment process itself typically runs four to six years for a genuinely novel design, because the safety case has to be built from scratch rather than inherited from decades of large-reactor operating history. The UK’s Generic Design Assessment process for Rolls-Royce’s SMR started in 2022 and isn’t expected to conclude before 2027 at the earliest. Add construction, commissioning and the inevitable first-of-a-kind teething problems, and anyone promising an operating SMR on the NEM within this decade is not describing the real world as the regulators who’d actually have to approve it see it.

My own read, for what it’s worth, sitting on a verandah in Fremantle watching the shipping queue at Gage Roads some evenings when I should be doing something more useful: SMRs are a plausible 2040s technology for niche Australian applications, not a 2030s answer to the coal retirement schedule everyone’s actually arguing about. The debate we keep having – does Australia actually need nuclear power? – gets more honest the moment people stop treating SMRs as a near-term substitute for transmission and storage that we have to build regardless of what happens in the reactor world.

Agreeing on the units, one more time #

The short version, then: one demonstration unit running commercially in China, one strategic floating plant in the Russian Arctic, a handful of serious Western projects still years from first concrete or years from first power, and zero completed regulatory pathways anywhere near Australia’s own framework. That’s not a reason to stop funding the engineering work – ARENA and the CSIRO’s own GenCost modelling are right to keep tracking the cost trajectory as real projects report real numbers. But it is a reason to be deeply sceptical of anyone citing SMRs as the answer to a coal station closing in the next five years. The maths on what actually replaces that capacity (firmed renewables, transmission, batteries, gas peakers in the interim) is covered in enough detail elsewhere on this site that I won’t relitigate it here. The reactor that solves it hasn’t been licensed yet, let alone built.

– Tom Fitzgerald, Baseload & Fuels Correspondent