Eighty-two per cent. That’s roughly where Victoria now says its grid will sit on renewable generation by 2030, revised up from an earlier 65 per cent goal after the state’s energy department recalculated against faster-than-expected rooftop solar uptake. Queensland says 70 per cent by the same year. NSW doesn’t actually run a single headline renewables percentage target at all. It runs a legislated electricity supply objective and a REZ capacity framework instead. Three states, three different units of measurement, and a public debate that treats them as if they’re the same thing.
They’re not.
I’ve spent a fair chunk of the past month pulling target documents off state government websites, partly because a reader in Ballarat emailed asking why Victoria’s target “jumped” and partly because the comparison gets mangled in almost every political press release I read. The honest read is that state renewable energy targets are not a competition with a scoreboard. They’re policy instruments built on different baselines, different accounting conventions and, in at least two cases, different definitions of what counts as renewable in the first place.
What the headline numbers actually measure
Start with the basic trap. When a state says “50 per cent renewables by 2030,” does that mean 50 per cent of electricity generated within the state, 50 per cent of electricity consumed, or 50 per cent of installed capacity? These are not interchangeable figures, and the gap between them can be enormous.
South Australia is the cleanest illustration because it’s already blown past most of its own targets. The state’s own data, published through the South Australian Department for Energy and Mining, shows annual renewable generation now regularly exceeding full state demand on an average basis, with rooftop solar and wind combining to push the grid into net-exporter territory on sunny, windy days. That’s generation versus consumption accounted for over a full year, not instantaneous share. I wrote about why this state keeps teaching the rest of the NEM uncomfortable lessons in South Australia: the grid that keeps teaching the NEM lessons, and the short version is that SA got there mostly by accident of geography and a willingness to let the market do things first, policy paperwork second.
Victoria’s 2030 target is a share-of-generation figure benchmarked against the state’s own consumption forecast, which matters because that forecast keeps moving. Queensland’s 70 per cent target, set out in the state’s energy and jobs plan, is also generation-share but layered onto an explicit public-ownership commitment for new large-scale assets, which I’ve covered in detail in Queensland’s energy plan rests on pumped hydro and public money. NSW, by contrast, runs its Electricity Infrastructure Roadmap through REZ capacity auctions and a legislated objective rather than a single renewables percentage, which makes direct comparison with Victoria or Queensland close to meaningless unless you convert everything to the same denominator first. Almost nobody in the political commentary does that conversion. Follow the money and you’ll find the states with the loosest definitions are usually the ones furthest behind on actual steel in the ground.
The Western Australia problem
Here’s where the comparison really falls over. Western Australia’s South West Interconnected System isn’t part of the NEM at all. It’s its own island grid with its own target regime, and because it has no interconnector to lean on, its renewable share has to be backed by its own storage and firming rather than imports from a neighbouring state having a good wind day. I went through the mechanics of that isolation in WA’s SWIS: the grid with no neighbour to call, and the upshot is that WA’s target numbers, while often quoted alongside NEM states in national tables, aren’t measuring the same risk profile at all. A 70 per cent target in a grid with interconnection to backstop it is a different animal to a 70 per cent target on an island.
Tasmania complicates things further by already claiming effectively 100 per cent renewable generation on paper, built almost entirely on legacy hydro rather than anything built this decade. That’s a genuine achievement from a different era of infrastructure, but it tells you very little about the pace of new build happening now. The honest comparison isn’t “who’s closest to 100 per cent”. It’s “who’s adding the most new firmed capacity per year relative to what they actually need.” On that measure Tasmania’s recent story is less about new renewables and more about whether the state can keep exporting its hydro advantage, a question that increasingly comes down to Tasmania’s Battery of the Nation bet still resting on one cable.
Legislated versus aspirational, and why it matters
Not all targets carry the same legal weight, and this is the bit that gets glossed over in almost every comparison table I’ve seen published.
Victoria’s target sits in legislation with periodic statutory reporting obligations attached. Queensland’s energy and jobs plan has budget appropriations and public ownership commitments tied to it, which gives it teeth even without the same legislative mechanism. NSW’s roadmap is underpinned by the Electricity Infrastructure Investment Act, which creates the REZ access scheme and long-term energy service agreements that effectively lock in contracted capacity regardless of which government is in office. These are meaningfully different levels of commitment. An aspirational target with no legislative or contractual backing can be quietly abandoned by the next minister with a press release. A target wired into contracted capacity payments is much harder to walk away from, because walking away means breaking commercial agreements with generators who’ve already financed projects against them.
This is the part that should worry anyone treating target percentages as a proxy for delivery confidence. A state can have an ambitious headline number and a weak delivery mechanism, or a modest headline number backed by hard contractual scaffolding. NSW’s REZ framework is the second type. Several of the state-level renewables percentage targets floated in recent years are closer to the first.
The transmission constraint nobody puts a number on
None of the headline targets say anything about whether the wires exist to move the power. This is the gap I keep coming back to, because it’s the one that actually determines whether any of these numbers get hit on schedule.
Take the Central-West Orana zone in NSW, which has a healthy project pipeline and a generation target implicit in its REZ declaration, but the transmission works needed to fully unlock it remain behind schedule, a story I went through in Central-West Orana REZ: NSW’s first zone still half-wired. Queensland’s CopperString project carries similar exposure; the renewables target assumes northern and western capacity that depends on a transmission line still working through its own construction timeline, covered in Powerlink’s CopperString bet: the wire to the north-west. A renewables percentage target published on a government website is a demand-side number. Whether it’s achievable is a supply-side, poles-and-wires question, and the two documents are almost never read together by the people quoting the headline figure in Question Time.
My mildly unpopular view here: I think several of the more ambitious state targets function less as delivery plans and more as political signalling devices aimed at investors and the Commonwealth, with the actual delivery risk quietly outsourced to AEMO’s Integrated System Plan and to transmission businesses who then cop the blame when timelines slip. The ISP itself, which I went through line by line in What the AEMO Integrated System Plan actually says, is far more conservative about near-term delivery than most state target documents let on. That mismatch between the state target rhetoric and the system planner’s own modelling isn’t an accident. It’s a function of two different documents written for two different audiences, one for voters and one for investors who need the caveats spelled out properly.
What a fair scorecard would measure
If I were building a genuinely comparable scorecard across states, I’d throw out the headline percentage entirely and measure four things instead: contracted new-build capacity per year against the connection queue actually progressing, transmission augmentation milestones hit on schedule, firming capacity (storage plus dispatchable gas or hydro) added per gigawatt of variable renewables connected, and legislative or contractual lock-in behind the stated target. None of these show up in a press release because none of them make for a clean soundbite. But together they’d tell you far more about whether a state is actually on track than any percentage figure measured against a moving consumption forecast.
AEMO’s own published data through its quarterly dashboards, and the Clean Energy Regulator’s Large-scale Renewable Energy Target data, give a reasonable public proxy for the capacity side of that scorecard, even without a unified state-by-state comparison tool existing yet. The Clean Energy Regulator tracks accredited large-scale generation certificates nationally, which at least offers a common unit across state borders, something the state target documents themselves conspicuously avoid providing.
The part that gets missed in election years
Every state election cycle, someone resurrects the renewables target league table, usually ranking states from “most ambitious” to “least ambitious” based on the headline number alone. It’s a lazy exercise and, frankly, a bit of a cricket-commentary equivalent of judging a batter purely on strike rate without checking how many deliveries they actually faced. A state with a modest target backed by contracted capacity and functioning transmission will beat a state with an aspirational 80 per cent figure and a REZ still waiting on its main transmission corridor, every time, on the measure that actually matters: megawatt-hours delivered to consumers at a price that doesn’t spike every still, cloudy evening.
Victoria’s revised 82 per cent figure, Queensland’s 70 per cent, WA’s island-grid trajectory and NSW’s REZ-based roadmap are all defensible policy choices given each state’s starting position. What they are not is comparable on a single axis, and the public debate would be a lot more useful if commentators stopped pretending otherwise. Worth asking your own state energy minister, next time one fronts a press conference with a shiny new percentage, exactly what denominator sits underneath it, and whether the transmission business responsible for delivering it has actually said the date is achievable.
– Marcus Wren, Editor