Grid & Storage

Tasmania runs on hydro, but one cable decides its future

23 November 2026 · by Anjali Rao
8 min read·1796 words·Updated 23 Nov 2026

Ninety-odd per cent. That’s roughly the share of Tasmania’s own generation that comes out of Hydro Tasmania’s fleet in an average year, and it has been true in some form since before most of the people now running the National Electricity Market were born. I spent a chunk of this year going back through Hydro Tasmania’s annual filings and AEMO’s Tasmanian supply-demand data, and the thing that struck me wasn’t the hydro share itself. It was how little that share has changed in seventy years, while the plan sitting on top of it has become one of the most ambitious rewrites of a state grid anywhere in the country.

Tasmania doesn’t have a coal closure to manage. It doesn’t have a rooftop solar glut flooding the middle of the day, not in the way the mainland’s distribution networks are dealing with. What it has is 30-odd hydro power stations, a chain of lakes that function as enormous slow batteries, and a single undersea interconnector to Victoria that was never quite big enough for what everyone now wants it to do.

The hydro system is already a battery, just not the kind people picture #

Here’s the distinction I try to get people to sit with: Tasmania’s hydro scheme was never built as peaking plant in the way a modern battery is. It was built as a managed water system, storing rainfall in dam catchments across the Central Highlands and the west coast, then releasing it through turbines according to a mix of seasonal inflow, irrigation and environmental requirements, and electricity demand. The storage is measured in gigalitres, not megawatt-hours, and the translation between the two depends on which station you’re talking about and how full the lake is.

That matters because when people say Tasmania is “basically one big battery”, they’re using the word loosely. A battery like the Hornsdale installation in South Australia can go from zero to full output in under a second and empty itself in an hour or two. Tarraleah or Gordon can ramp fast too, but their real value isn’t speed, it’s duration. Gordon’s storage alone can theoretically run for months. That’s a genuinely different asset class to a four-hour lithium battery, and it’s the reason Tasmania keeps getting cast as the answer to the mainland’s firming problem rather than just another state with a renewables surplus.

What Battery of the Nation actually proposes #

Battery of the Nation is Hydro Tasmania’s umbrella name for turning existing hydro assets, upgraded hydro capacity and new pumped hydro into a resource the rest of the NEM can draw on, not just Tasmanians. The pitch is straightforward on paper: Tasmania already has deep, flexible storage. Victoria and the mainland grid increasingly need deep, flexible storage as coal retires and variable renewables take a bigger share of generation. Build enough transmission between the two and Tasmania’s water becomes the mainland’s shock absorber.

The flagship piece of new hardware under this banner is the proposed pumped hydro development at Tarraleah, upgrading an existing scheme, alongside work on Cethana as a pumped hydro candidate. Both would use existing dam infrastructure rather than starting from a green paddock, which keeps the capital cost down relative to a project like Queensland’s Borumba scheme, which I wrote about when I went through its cost and timeline. But “lower than Borumba” is not the same as cheap, and neither Tarraleah nor Cethana has reached a final investment decision as of now. They’re both sitting in the feasibility-to-approvals stage, which in Australian transmission and generation projects lately has proven to be where schedules go to get revised upward.

None of the Battery of the Nation story works without more cable under Bass Strait. Tasmania already has Basslink, a single 500-odd megawatt interconnector that has been running since 2006 and has had its share of outages, including a lengthy failure in 2015-16 that left the state scrambling for diesel generation and water restrictions on the hydro scheme at the same time. One cable, one point of failure, and Tasmania found out the hard way what that meant.

Marinus Link is meant to fix that by adding a second, larger connection. I’ve covered the project’s cost and staging in detail in an earlier piece on where the numbers actually sit, so I won’t re-run the whole history here, but the short version for this profile is that Marinus has been staged into two 750 megawatt cables rather than built as one larger link, construction timelines have already slipped more than once, and the project’s capital cost has moved in the direction most transmission costs in this country have moved lately, which is up. TasNetworks and Marinus Link Pty Ltd, the joint venture now majority owned by the Commonwealth and Tasmanian governments after Victoria stepped back its equity position, continue to describe the project as proceeding, with the first cable targeted for commissioning later this decade.

Let’s be careful with that number, though, because “later this decade” has already moved once since the project was first announced, and transmission builds of this scale (subsea, trenched, crossing some genuinely difficult terrain on both the Tasmanian and Gippsland ends) have a track record of moving again. I’d put real money on a further schedule slip before the second cable is in service, not because the engineering is impossible but because every comparable project in this country, from HumeLink to VNI West, has taught us the same lesson about contractor availability and landholder negotiation timelines.

Power versus energy, and why the interconnector size argument gets muddled #

This is where I want to slow down, because it’s the part of the Battery of the Nation pitch that gets collapsed in a lot of coverage. Marinus Link adds transfer capacity, measured in megawatts, the rate at which electricity can move across Bass Strait at any instant. Tarraleah and Cethana, if built, add storage capacity, measured in megawatt-hours or more precisely in the reservoir volumes that convert to megawatt-hours over time. These are not substitutes for each other. You can build a bigger cable and still not have enough stored energy behind it to use that capacity for more than a few hours at a stretch during a dry year. You can build more pumped hydro storage and still be bottlenecked getting the output to the mainland if the cable’s too small.

AEMO’s Integrated System Plan treats Marinus and the Tasmanian storage additions as a paired investment for exactly this reason: one without the other doesn’t deliver the claimed benefit. The 2024 ISP update from AEMO models Tasmanian hydro and pumped hydro as part of the firming capacity the NEM needs through the 2030s and 2040s, but that modelling assumes both pieces get built roughly on the timelines proposed. If Marinus slips further while Tarraleah proceeds, Tasmania ends up with stranded storage capacity it can’t export. If Marinus gets built first and the pumped hydro upgrades stall, the cable’s value proposition shrinks to shuffling existing hydro output around rather than adding new flexible capacity to the system.

The capacity factor argument nobody runs for hydro #

I wrote a piece a while back on why a lower capacity factor can still be the better asset, using the framing that a 30% capacity factor generator that shows up exactly when the grid needs it beats a 90% capacity factor generator than runs flat regardless of demand. Tasmanian hydro is the clearest real-world example of this principle I know of. Hydro Tasmania doesn’t run its stations at maximum output continuously, it holds water back and releases it strategically, which means the fleet’s realised capacity factor across a year can look unremarkable on paper while its actual grid value, in terms of dispatchability when the mainland needs firming, is enormous. Any comparison of Tasmania’s generation mix to, say, a coal state’s that just lines up annual output totals is missing the entire point of what the asset is for.

What this means for Tasmanian consumers, not just the mainland #

It’s worth separating two audiences in this story, because they don’t always want the same outcome. Mainland energy planners want Tasmania’s storage exported north to firm variable renewables in Victoria and beyond. Tasmanian households and industry, particularly the energy-intensive smelting and processing operations around the Tamar Valley and in the state’s north-west, want secure, reasonably priced local power first. Those two goals aren’t necessarily in conflict, but they’re not automatically aligned either, and the state government’s own energy policy documents have had to wrestle with how much of the hydro scheme’s output gets reserved for local use versus sold into an expanded interstate market once Marinus is operational.

There’s also a straightforward public ownership question running underneath all of this. Hydro Tasmania is a state-owned corporation, TasNetworks is state-owned, and the Marinus joint venture is now majority government-owned following the Commonwealth and Tasmanian funding arrangement. That’s a genuinely different ownership model to the private gentailer-dominated structure you see in a comparison of AGL and Origin’s strategies, and it’s closer to the public-asset model Queensland has leaned into with its own pumped hydro build, which I covered in a piece on Queensland’s energy plan. Whether public ownership builds this kind of long-duration infrastructure faster or slower than a private developer would is a genuinely open argument, and I don’t think the Tasmanian case settles it either way yet, the project’s too early.

A system with one obvious weak point and no quick fix for it #

My contrarian take, and it’s a mild one: I think Battery of the Nation gets spoken about as though the hard part is the hydro engineering, when the hydro engineering is actually the known quantity. Hydro Tasmania has been running this scheme since the Hydro-Electric Commission days and the geology, the catchments, the turbines, all of that is well understood. The genuinely uncertain part of this whole story is a subsea and overland transmission cable crossing one of the more exposed stretches of water in the country, built by a workforce and supply chain that’s stretched thin across half a dozen other transmission projects nationally. If I had to bet on which piece of Battery of the Nation slips its schedule next, it wouldn’t be the pumped hydro.

I came off a long ride through the Derwent Valley earlier this year, past the Meadowbank and Cluny dams, and it’s hard not to be struck by how quiet and permanent the whole system looks from the road. No cranes, no construction noise, just water doing what it’s done for decades. Marinus Link is the opposite kind of project entirely, loud, visible, contested in places along the route, and years from being finished. Tasmania’s energy future depends on both pictures turning out right at roughly the same time.

– Anjali Rao, Grid & Storage Correspondent