Capacity factor: why 30% can beat 90% on the grid

A new solar farm near Dubbo publishes a nameplate of 333 megawatts. A gas peaker at Kurri Kurri is rated around 660 megawatts. On paper the gas plant looks like it does twice the work. In practice, over a full year, the solar farm will probably generate more electricity than a peaker that mostly sits […]
HumeLink’s cost has nearly tripled. Where the project actually stands

$4.9 billion. That’s the current estimate for HumeLink’s capital cost, up from an original figure north of $1.3 billion when Transgrid first put the project to the market in the early stages of planning. I’ve sat through enough regulatory determinations to know cost escalation on big transmission is common, but a rise of this size […]
Transgrid: the wires company three REZs are waiting on

Three hundred and sixty kilometres. That’s roughly the length of the HumeLink easement running from Wagga Wagga to Bannaby, cutting through the Snowy Mountains foothills and some of the more fought-over grazing country in southern NSW. It’s also, as of late 2026, still not fully energised end to end, even though the project was meant […]
CopperString 2032: Powerlink’s 1,100km bet on the north-west

Mount Isa has been running on an island grid for longer than most of its residents have been alive. Diesel and gas-fired generation, a transmission network that stops well short of connecting to the National Electricity Market proper, and a minerals province sitting on some of the better copper, cobalt and rare earth prospects in […]
Central-West Orana REZ: NSW’s first zone, still half-wired

Drive the Golden Highway between Dunedoo and Merotherie on a clear day and you’ll see the paddocks that are meant to carry a fair slice of NSW’s coal replacement. Turbines at Liverpool Range, solar arrays staged near Narromine and Dubbo, and underneath all of it, still being dug in, the transmission that’s supposed to connect […]
Virtual power plants, explained

AGL’s latest investor update puts its virtual power plant fleet at something north of 200 megawatts of aggregated capacity across home batteries, pool pumps and controllable loads. Origin runs a comparable programme. Neither number sounds like much next to Eraring’s 2,880 megawatts of nameplate coal capacity. But a virtual power plant isn’t trying to be […]
AusNet after Brookfield: the wires owner building Western Renewables Link

Drive the Western Highway out past Bacchus Marsh and you’ll start seeing the easements being cleared for steel lattice towers, wide brown scars cutting across paddocks that haven’t had anything bigger than a grain silo on them in a century. That’s Western Renewables Link under construction, and it’s the project that tells you most of […]
Powerlink’s CopperString bet: the wire to the north-west

Mount Isa sits roughly 900 kilometres west of Townsville by road, and for as long as the mine there has been running, the town has generated most of its own power off gas because there has never been an economic case to string transmission that far from the coastal grid. That is the gap Powerlink […]
Waratah Super Battery: the shock absorber earning its keep

850 megawatts of power, 1,680 megawatt-hours of energy, sitting on a former coal ash site at Munmorah on the NSW Central Coast. That’s the Waratah Super Battery in two numbers, and I’d argue most coverage of this project still gets the relationship between those two figures backwards. The power rating is what matters here. The […]
Collie battery: the two big storage bets replacing WA coal

Drive south from Bunbury on the Coalfields Highway and you hit Collie before you’ve finished your coffee: a town of maybe 9,000 people that has run Western Australia’s coal fleet for the better part of sixty years. What’s going up on the outskirts now, next to switchyards that used to only ever move power one […]