What the AEMO Integrated System Plan actually says

24 November 2026 · by Anjali Rao
7 min read·1521 words·Updated 24 Nov 2026

I had a federal MP’s staffer quote the Integrated System Plan to me last month as proof that “AEMO says we need nuclear by 2040.” The document says no such thing. It doesn’t model nuclear at all in its central scenario, and where it does touch on new technologies not yet commercially proven in Australia, it treats them as a sensitivity, not a recommendation. That gap between what the ISP actually contains and what people claim it says has become one of the more persistent pieces of misinformation in the Australian energy debate, and it’s worth sorting out properly rather than in a six-second grab on the radio.

The ISP is published every two years by the Australian Energy Market Operator, with the most recent full version released in mid-2024 and an interim update process running since. It is, formally, a roadmap for the National Electricity Market’s transmission and generation investment over the next twenty years, built to satisfy AEMO’s obligations under the National Electricity Rules. It is not legislation. It is not a government policy document. It is a planning model, produced by engineers, that gets treated in public debate as something closer to scripture.

What the document is actually for #

AEMO’s own framing is that the ISP identifies the least-cost pathway to reliably supply the NEM as coal retires, demand grows and generation mix shifts. That “least-cost” qualifier matters more than most coverage lets on. The ISP isn’t predicting what will happen. It’s modelling what should happen, under a defined set of assumptions, if the objective is minimising the cost of a reliable, secure grid while meeting Australia’s emissions commitments under current policy settings.

The plan runs multiple scenarios, not one forecast. The current iteration includes a “Step Change” scenario as the most-used reference case, alongside others that vary the pace of electrification, industrial demand growth and policy ambition. Anyone who quotes “the ISP says X megawatts of wind by 2035” without naming which scenario they’re reading from the Step Change central case isn’t being precise, and precision is the whole point of the exercise.

The optimal development path, not a construction schedule #

The centrepiece of each ISP is what AEMO calls the optimal development path, a sequenced build-out of transmission and generation that the model finds minimises total system cost across the planning horizon. It includes transmission projects like HumeLink and VNI West, firming capacity, and a rough trajectory for new wind, solar and storage capacity by region.

Let’s be careful with that number, because this is where I see the most slippage in how people use the document. The optimal development path is a modelling output, generated by AEMO’s own market modelling software under the assumptions fed into it. It is not a construction timetable that Transgrid, AusNet or Powerlink are contractually bound to hit. Projects in the path still need regulatory approval through the AER’s revenue determination process, environmental approvals, landholder negotiation and actual construction contracts before a single tower goes up. I’ve written before about how HumeLink’s cost has nearly tripled from its original estimate, and that cost blowout happened entirely within the window the ISP assumed the project would proceed on budget. The plan told everyone what should happen. It didn’t guarantee what would.

Where the gigawatt numbers actually come from #

Every year someone writes that “the ISP says Australia needs 10,000 kilometres of new transmission” or some similarly round figure, usually lifted from a press release rather than the document itself. The real numbers are regional and staged across multiple investment periods out to 2050, broken down by Renewable Energy Zone, and they shift meaningfully between iterations as cost estimates, demand forecasts and committed projects change.

A worked example helps here. Say the ISP models 2,000 MW of new wind capacity for a given REZ by a certain milestone year. That is a nameplate capacity figure, not an energy delivery figure. At a typical onshore wind capacity factor in the high-30s to low-40s per cent range, 2,000 MW of nameplate might deliver somewhere around 700 to 850 MW of average output across a year, which is the number that actually matters for displacing coal generation. I’ve gone through this distinction before when I wrote about why capacity factor matters more than nameplate numbers suggest, and it applies just as directly to reading the ISP as it does to reading a developer’s press release. Power and energy are different units. The document is careful about this distinction internally. A lot of the commentary built on top of it isn’t.

The scenarios people conveniently forget to name #

AEMO doesn’t just publish one future. The current ISP cycle runs scenarios that vary assumptions on electrification uptake, hydrogen export demand, the pace of coal retirements and broader economic settings. Step Change remains the primary scenario AEMO uses for its own planning recommendations, largely because it reflects current stated government policy and a realistic trajectory of consumer electrification.

But there’s also a “Progressive Change” scenario with slower uptake, and scenarios that stress-test higher industrial and hydrogen demand. When someone cites a figure from the ISP, ask them which scenario it’s from. In my experience, most people haven’t checked, including some people whose job title suggests they should have. It’s a small thing, but it’s the difference between a quote being defensible and a quote being decorative.

What it says about coal, gas and reliability #

The ISP assumes coal retirements broadly in line with generator-announced closure dates, adjusted where AEMO’s own reliability modelling suggests risk. This is part of why the document has become a reference point in debates like the one I covered around whether coal is closing faster than the replacement capacity can be built. The plan doesn’t argue coal should close on a faster or slower timeline out of ideology. It models the system cost and reliability consequences of the closure dates generators have themselves nominated, and flags where the development path needs to accelerate to avoid a reliability gap.

On gas, the ISP treats existing and some new gas peaking capacity as part of the firming mix through the transition, not as a technology being phased out entirely by a fixed date. That’s consistent with what I found when I looked at how gas peakers and big batteries actually compete for the firming job: gas doesn’t disappear from AEMO’s modelling, it shrinks in relative share while batteries and pumped hydro take on more of the short-duration firming task.

My honest read on how it gets used #

Here’s my mildly unpopular opinion on this, and I’ll own it: I think the ISP is a genuinely good piece of engineering work that gets dragged into fights it was never built to settle. It’s a least-cost optimisation under stated assumptions, produced by a market operator with a statutory planning function. It was never meant to be a political mandate, and treating it as one, in either direction, whether to justify a transmission project’s cost blowout or to claim it endorses a technology it barely mentions, misuses a genuinely careful piece of modelling.

If I have a real criticism, it’s that AEMO’s own public communication around the ISP could do more to flag the difference between “this is what the model finds is least-cost under these assumptions” and “this is what will happen.” The caveats are all in the document; AEMO’s Draft and Final ISP releases run to hundreds of pages with explicit sensitivity tables. But caveats buried on page 140 don’t survive contact with a press release headline, and that’s not really AEMO’s fault so much as it is everyone downstream of the document choosing the convenient half-sentence.

Reading it properly if you’re going to cite it #

If you’re going to quote the ISP, go to AEMO’s own published document rather than a secondary summary. Check which scenario the figure comes from. Check whether the number is capacity or energy. Check the publication date, because the ISP gets updated and the 2024 figures have already shifted in places as projects like VNI West have run into real-world delay and cost revision. None of that makes the plan less useful. It makes it a living document rather than a prophecy, which is a less satisfying thing to put in a tweet but a far more accurate description of what AEMO actually built.

I keep a printed copy of the Draft ISP on my desk, mostly because I find the regional REZ maps easier to annotate on paper than on a screen, and more than once I’ve had someone in a briefing room quote a figure from memory that the actual table contradicts. It’s a bit like correcting someone’s chess notation mid-game: nobody enjoys being the pedant, but the board doesn’t care about your feelings, and neither does a planning document with real dollars attached to its assumptions.

For AEMO’s own description of the document’s methodology and the latest published tables, the 2024 Integrated System Plan and its supporting data are available directly through AEMO’s major publications page, alongside the AER’s separate transmission revenue determination process referenced at aer.gov.au, which governs whether the projects in the optimal development path actually get funded.

– Anjali Rao, Grid & Storage Correspondent