Drive the Esplanade at Port Albert on a grey morning and you’ll see exactly nothing that tells you an offshore wind zone sits a few dozen kilometres out past the horizon. No barges, no jack-up vessels, no turbine blades stacked on a wharf. Just the usual mix of fishing boats and a bloke walking a dog along the foreshore. That gap between the paperwork and the seascape is the whole story of the Gippsland offshore wind zone right now, and it’s worth being blunt about it before the spruiking starts again.
The Gippsland zone was the first area declared under the federal offshore electricity infrastructure framework, back in December 2022, covering roughly 15,000 square kilometres off the Victorian coast. It was meant to be the proof of concept for the whole industry – closer to shore than most people expected, close to the Latrobe Valley transmission corridor that’s about to lose Yallourn, and close to a workforce that’s spent generations building things offshore for Bass Strait oil and gas. On paper it still ticks every box. In practice, three years on, the Gippsland offshore wind zone has feasibility licences and very little else to show for it.
Where the licences actually sit
The Clean Energy Regulator and the Department of Climate Change, Energy, the Environment and Water handled the initial licensing round, and several proponents hold feasibility licences across the Gippsland zone, including Star of the South, which has been the most advanced and most publicly scrutinised of the lot. A feasibility licence isn’t a construction approval. It buys you the right to put met masts in the water, run geotechnical surveys, model wake effects and figure out seabed conditions: the unglamorous groundwork that turns a nameplate figure into an actual engineering plan. It does not buy you a grid connection, an environmental approval under the EPBC Act, or a commercial agreement to sell the power.
Star of the South, a joint venture between Ørsted and a local development partner, has talked up a project in the vicinity of 2.2 gigawatts if it’s built out in full: enough, on its own modelling, to power a meaningful slice of Victorian households. I’d treat that number the way I treat every offshore wind figure at this stage: as the top of a range that depends on turbines being bigger, foundations being cheaper and the connection agreement actually closing. Readers of this site know my view on turbine-count claims generally – see the comparison in onshore versus offshore wind in Australia, and Gippsland is no exception. Capacity factor matters more than the headline megawatt figure, a point this site has made before in the capacity factor explainer, and offshore wind’s higher capacity factor is genuinely one of its strongest selling points. But capacity factor doesn’t fix a transmission bottleneck.
The grid connection problem
This is where Gippsland’s advantage gets complicated. The zone sits near the existing Latrobe Valley transmission infrastructure, which is a real asset. Those lines were built to carry coal-fired baseload out of the valley and some of that capacity will free up as Yallourn and Loy Yang close out across the back half of this decade. AEMO’s Integrated System Plan leans on exactly this logic, treating Gippsland offshore wind as a long-run replacement for Latrobe Valley coal capacity rather than a bolt-on. The detail of that plan is worth reading properly rather than taking on faith, and I’d point readers to the earlier piece on what the AEMO Integrated System Plan actually says for the caveats AEMO itself attaches to its own offshore wind assumptions.
The catch is timing. Transmission upgrades and new connection infrastructure take years to plan, approve and build, and nobody has broken ground on dedicated offshore wind transmission in Gippsland yet. VicGrid, the state body set up to coordinate Victorian transmission planning, has been doing early work on a offshore wind transmission corridor, but a planning study is not a connection agreement, and a connection agreement is not steel in the ground. Star of the South’s own public statements have pushed back the timeline for a final investment decision more than once since the project was first proposed back in 2012 under its original name. That’s not a criticism specific to this developer. It’s the pattern across every early-stage offshore project in a market with no existing supply chain, no local vessel fleet and no established marine construction precedent.
The community pushback that won’t go away
Anyone who’s sat through a Gippsland offshore wind community session knows the arguments by now. Commercial fishing operators around Lakes Entrance and the wider Gippsland fleet have raised concerns about exclusion zones and cable corridors cutting through traditional fishing grounds. Tourism operators along the Ninety Mile Beach worry about sightlines, even though the zone sits far enough offshore that visibility from the beach is genuinely contested – on a clear day you might make out a turbine tip, on most days you won’t. And there’s a vocal strand of local opposition that’s organised around amenity and property value concerns, echoing debates seen at Illawarra and other proposed zones.
I don’t think this opposition should be waved away as simply uninformed, and I don’t think it should be treated as determinative either. The federal offshore framework requires a management plan process with formal consultation, and Star of the South and other proponents have run community information sessions across Sale, Yarram and other Gippsland towns. Some of the concerns raised (about fishing ground displacement, about cumulative visual impact if multiple projects proceed) are legitimate planning questions that deserve a proper answer in the environmental approval process, not a line in a glossy brochure. Where I’d push back on some of the louder objections is the claim that offshore wind represents some unprecedented industrialisation of the coast. Bass Strait has had oil and gas platforms visible from parts of the Gippsland coastline for over fifty years. The region isn’t being asked to accept heavy industry at sea for the first time; it’s being asked to accept a different kind of heavy industry at sea.
The economics nobody wants to say out loud
Offshore wind is expensive to build relative to onshore wind or solar, and it’s expensive in a specific way: the capital cost is front-loaded into vessels, foundations and subsea cabling before a single megawatt-hour gets sold. Global offshore wind costs have risen sharply since 2022, driven by vessel day-rates, steel costs and supply chain bottlenecks that hit UK and US projects hard enough that some were cancelled or renegotiated. Australia doesn’t have a mature local offshore wind supply chain at all: no local foundation fabrication at scale, no local installation vessel fleet, no established port handling capacity purpose-built for turbine components the size these projects need. Portland and Geelong have both been discussed as potential marshalling ports, and neither currently has the laydown area or quayside infrastructure fully built out for it.
That means Gippsland projects are, in effect, importing almost the entire supply chain, which adds cost and adds schedule risk that onshore projects in places like the Central-West Orana REZ simply don’t carry to the same degree: a point worth sitting with given how slowly even that REZ’s transmission has rolled out, as covered in Central-West Orana REZ: NSW’s first zone, still half-wired. The federal government’s Capacity Investment Scheme has carved out allocations intended to support offshore wind specifically, recognising that it won’t clear on cost alone against onshore wind and solar in a reverse auction. Whether that support is sufficient to get Star of the South to a bankable final investment decision is the open question nobody in Canberra or at AEMO has definitively answered yet.
What Victoria is actually betting on
The Victorian government’s own target, set under its offshore wind policy framework, points to multiple gigawatts of offshore capacity by the early 2030s and more again by 2040, with Gippsland doing most of the heavy lifting alongside the smaller southern coast zones. That target sits inside a broader state energy strategy that also includes the revived State Electricity Commission, a public entity now taking equity positions in renewable generation: a dynamic I’d flag readers back to in Victoria’s SEC revival meets its offshore wind test, because the SEC’s willingness to co-invest could end up being more decisive for Gippsland’s timeline than any federal licensing round.
Clean Energy Council figures and AEMO’s published generation information page both still list Gippsland and Star of the South as committed or anticipated projects rather than operating ones, which is the correct classification. There’s a meaningful difference between a project that’s secured a feasibility licence and a project that’s secured finance, and conflating the two is how every offshore wind story in this country ends up overpromising.
The honest read
I reckon Gippsland remains the best-positioned of Australia’s declared offshore wind zones: better than Illawarra on proximity to existing transmission, better resourced in terms of wind quality, and sitting in a state government that’s actually willing to put equity behind it. None of that changes the fact that the project pipeline here is still measured in licences and surveys, not megawatts delivered. The gap between a 2.2 gigawatt headline and an actual connection agreement is the only number that matters, and right now nobody’s published one.
Next time I’m down that way I’ll swing past Port Albert again and see if there’s anything new on the water. For now, the fishing boats still outnumber anything flying a wind developer’s flag, and that tells you roughly where this project sits on the curve from announcement to operation.
– Callum Hayes, Wind & Offshore Correspondent