Two hours. That’s roughly the storage duration of most big batteries currently operating in the National Electricity Market. Not four hours, not eight: two. Which is an odd design choice for a technology routinely marketed as the thing that will carry the grid through the evening peak after the sun drops and the wind goes quiet.
I’ve spent a chunk of this month going back through AEMO’s battery data and a handful of recent connection applications, and the pattern holds pretty consistently across the fleet. The honest read is that most of what’s being built right now isn’t sized for firming at all. It’s sized for arbitrage: buy cheap, sell dear, turn the battery over two or three times a day, and bank the spread. That’s a perfectly legitimate business. But it’s not the same job the public conversation thinks these things are doing, and the gap between the two is starting to matter.
What the two-hour design actually tells you #
A two-hour battery can chase the midday solar trough and the evening price spike, charge again overnight if the spread’s there, and be home in time for the next cycle. It’s a trading asset dressed up in grid-security language. Compare that with what a genuine firming asset needs to do: hold charge through an extended wind lull, cover a four-to-six-hour evening ramp when coal units are tripping offline one after another, or bridge a multi-day heatwave event where demand stays elevated into the small hours.
Two hours doesn’t do that. It does the first fifteen minutes of that problem very well, then it’s empty and the operator is back to whatever’s left in the stack, usually gas, sometimes an interconnector pulling hard, occasionally not quite enough of either.
None of this is secret. AEMO’s own Integrated System Plan modelling assumes a mix of battery durations growing over time, with the longer-duration assets arriving later in the build-out as the economics catch up. The near-term fleet being financed today skews short because two-hour projects pencil out faster. That’s not a flaw in the plan. It’s a signal about what’s actually bankable right now, and it’s worth being honest about the difference.
Follow the money into the revenue stack #
Follow the money and the design choice stops looking strange. A battery earns from energy arbitrage, from the frequency control ancillary services markets, and increasingly from contracted capacity payments under state schemes or the Capacity Investment Scheme. Of those three, arbitrage and FCAS reward speed and cycling, not duration. A battery that can charge, discharge, charge again and chase every price swing in a day earns more per megawatt of capacity than one sitting there holding reserve for a once-a-fortnight stress event.
Developers aren’t stupid. They’re building the asset the market actually pays for. The problem is that the market signal and the system need have drifted apart, and nobody’s forced them back together yet. I’d argue that’s the real story here, more than any individual project’s numbers: the revenue stack is quietly steering fleet design away from the reliability job regulators keep implying batteries will do.
The Waratah Super Battery in NSW is the interesting exception that proves the point. It wasn’t built primarily to arbitrage energy prices. It exists to provide system strength and absorb shocks on the transmission network, a genuinely different function to a four-hour merchant battery sitting in western Victoria chasing the evening spread. Our profile of Waratah’s role as the grid’s shock absorber goes into that distinction properly. It’s a reminder that “big battery” covers several genuinely different jobs, and lumping them together in headlines does nobody any favours.
The comparison nobody wants to run #
Put a two-hour battery fleet next to the gas peaker fleet it’s supposedly replacing and the comparison gets uncomfortable fast. Gas peakers are expensive to run and carry emissions nobody’s proud of, but they can sit there for six, eight, twelve hours if the fuel supply holds. We’ve covered that trade-off in detail – see gas peakers versus big batteries on the firming job, and the mechanical truth hasn’t shifted since: batteries win on speed and efficiency over short windows, gas still wins on endurance. A fleet of short-duration batteries doesn’t retire gas. It just means gas gets called on for the harder shifts, which is exactly what’s happening at Kurri Kurri and a string of other peaking projects that keep finding work despite the renewables build-out around them.
There’s also a capacity factor angle worth sitting with. We’ve written before about why a low capacity factor asset can still be more valuable than a high one, depending on when it runs – see capacity factor explained. A two-hour battery has an inherently low utilisation ceiling by design. That’s fine if it’s priced correctly into the market. It’s a problem if planners quietly assume the fleet behaves like something with twice the duration.
Why the Capacity Investment Scheme nudges toward longer duration – slowly #
The federal Capacity Investment Scheme has started building duration requirements into its tender design, and that’s the right instinct. Longer contracted duration gets rewarded in recent CIS rounds, which should, over several years, pull the average fleet duration up from two hours toward four and beyond. The Clean Energy Regulator and AEMO both publish data tracking committed and operating battery capacity, and the direction of travel on duration is genuinely improving, project by project.
But “improving slowly” and “adequate for the 2028–2030 reliability window” are two different claims, and I think the sector conflates them more than it should. AEMO’s reliability standard work keeps flagging the mid-decade years as the tightest, precisely as coal units like Yallourn and Eraring step down. We’ve covered Yallourn’s 2028 closure and the battery racing the clock and the Eraring extension deal that bought NSW a couple of extra winters – neither buys much patience for a fleet still dominated by short-duration assets learning to go long.
The mildly contrarian bit #
Here’s where I’ll part ways with some of the cheerier commentary doing the rounds. The consensus view, repeated at most industry conferences I’ve sat through this year, is that battery storage capacity numbers in gigawatts are the headline that matters, and duration will sort itself out as the market matures. I reckon that’s backwards. A gigawatt of two-hour batteries and a gigawatt of eight-hour batteries are not remotely the same system asset, and treating the topline capacity number as the measure of progress flatters a fleet that, on current build trends, still isn’t shaped for the job the public thinks it’s doing.
It’s a bit like judging a bowling attack purely on wickets taken without asking whether they came in a dead rubber or a tight fourth innings chase. The number looks the same on the scorecard. The job done is completely different.
None of this means batteries are a bad bet. They’re clearly not: the economics of chasing volatile prices are sound, and every two-hour unit that comes online still takes pressure off something. But the industry and its boosters need to stop implying the current fleet is quietly solving the multi-hour reliability problem when the revenue incentives are steering most projects somewhere else entirely.
What actually needs to change #
Three things would close the gap, and none of them are radical. First, AEMO and the AER could be clearer in public communication about distinguishing short-duration trading assets from genuine firming capacity – right now both get reported under the same “big battery” banner and it muddies the public’s read on reliability. Second, CIS duration weighting needs to keep tightening, not just for new tenders but as a signal that flows back into merchant project design too. Third, state governments spruiking battery announcements, and there’s been no shortage of ribbon-cuttings this year – should publish duration alongside megawatt capacity as a matter of course, not as a footnote in the financial close statement.
Pumped hydro and long-duration storage projects like Borumba and Kidston are the longer-dated answer to the multi-hour problem, and we’ve tracked both projects’ slow progress toward commissioning. Batteries are faster to build and genuinely useful. They’re just not, in their current dominant form, the same tool as the one the headlines describe. Worth remembering the next time a developer announces another “grid-scale battery to power X thousand homes” – ask for the duration before you ask for the megawatts. The megawatts tell you the trading appetite. The duration tells you whether it’ll actually be there when the system needs it most.
– Marcus Wren, Editor