Stand on the headland at Sandon Point on a clear afternoon and you can just make out the edge of the declared zone, a smudge on the horizon well beyond where the container ships queue for Port Kembla. That distance matters more to this project than almost anything else in its development file, because it’s the single biggest concession the federal government made to get the Illawarra offshore wind zone declared at all.
The zone went from an original proposal of roughly 1,461 square kilometres down to about 1,022 square kilometres when then-Minister Tanya Plibersek signed off on the declaration in 2023, with the boundary pulled further offshore and trimmed around Kiama and the southern edge to address visual amenity and fishing industry concerns. That’s a smaller footprint than Hunter, smaller than Gippsland, and it was shrunk specifically because the Illawarra coast is narrow, steep and crowded with people who can see the water from their lounge rooms. I’ve driven the Grand Pacific Drive past Coalcliff and Clifton enough times to understand why the sightline argument landed with some force locally, even if I think the final boundary mostly reflects a political settlement rather than a technical one.
What’s actually been declared, and what hasn’t #
Declaration of the zone under the Offshore Electricity Infrastructure Act 2021 is a necessary step, not a commitment to build anything. It opens the area to feasibility licence applications, which is a different and much earlier stage than a connection agreement, an environmental approval, or a final investment decision. BlueFloat Energy, the Spanish-backed developer working the Illawarra prospect in partnership with Energy Estate, lodged for a feasibility licence covering a slice of the declared zone and has been running metocean and benthic survey work since. There is no approved project here yet. There’s a company holding, or applying to hold, the right to investigate one.
That distinction gets flattened constantly in coverage of offshore wind, and it’s worth being blunt about it: a feasibility licence tells you a company has paid for the option to find out whether a site works, not that the site works. The Illawarra zone sits in deeper water than the Hunter prospects further north, which pushes this firmly into floating turbine territory rather than fixed-bottom foundations, a technology gap I’ve covered in more detail comparing fixed-bottom and floating offshore wind. Floating offshore wind has no commercial-scale operating project in Australian waters, and very few anywhere in the world at the scale BlueFloat would need to make the Illawarra numbers work.
The megawatt number nobody should treat as fixed #
Early industry figures floated for the Illawarra zone talked about up to 2.9 gigawatts of potential capacity across the full area once the broader prospectus work was done. Treat that as a theoretical ceiling, not a project size. BlueFloat’s own public statements have been more conservative about what a first-stage development might actually look like, and the shrunken zone boundary mechanically caps how much can fit regardless of turbine spacing assumptions. Until there’s a defined project boundary within the declared area, a generation capacity figure, and crucially a connection point agreed with Transgrid or the relevant network business, any megawatt number attached to this project is an aspiration dressed up as an engineering fact.
And the connection question here is genuinely harder than it looks on a map. Port Kembla has existing heavy industry load and an ageing coal-adjacent grid architecture, not a greenfield REZ built with offshore wind in mind from day one. Unlike the Hunter zone, which sits near existing transmission corridors feeding out of the Hunter REZ works, the Illawarra’s connection options run through infrastructure that was built for a steelworks and a coal export terminal, not for gigawatts of variable offshore generation needing firm, high-capacity egress. Transgrid’s own planning documents acknowledge this corridor needs significant augmentation before any offshore wind connects at scale, work that sits well behind the HumeLink and Central-West Orana priorities already straining the business’s capital programme, something I’ve traced in more detail in my profile of Transgrid’s build-out queue.
Local opposition hasn’t gone away, it’s gone procedural #
The early protest signage around Wollongong and Kiama has largely given way to submissions, which is actually the more consequential shift. Groups including local fishing cooperatives and recreational fishers raised concerns through the feasibility licence consultation about exclusion zones overlapping productive grounds, and residents in coastal pockets from Thirroul down to Gerringong have pushed back on visual impact even with the boundary pulled further out. The Illawarra Offshore Wind Alliance and various community groups have been vocal, and some submissions explicitly challenge whether the shrunken zone’s distance from shore genuinely resolves the sightline issue or just makes the turbines slightly smaller on the horizon rather than invisible.
None of that opposition has stopped the feasibility phase. It has, however, shaped how cautiously the federal and state approvals processes are likely to move, and it’s added real time to a project that was never going to be fast. The NSW government’s own offshore wind consultation work has acknowledged community concern is more concentrated in the Illawarra than in the Hunter zone, partly because the coastline is more densely populated relative to its length and partly because Wollongong’s economy, unlike the Hunter’s, doesn’t have the same long association with heavy energy infrastructure sitting offshore in people’s minds.
BlueFloat’s wider Australian position #
BlueFloat is also working prospects in Gippsland and had been looking at other declared zones before the company’s global ownership and strategic priorities shifted, as they have across the floating offshore wind sector generally through 2025 and 2026. It’s worth saying plainly: floating offshore wind globally has had a rough run on costs, with several European and Asia-Pacific floating projects delayed or rescoped as developers confronted construction costs that ran well ahead of the fixed-bottom assumptions the sector had been using for planning. BlueFloat’s Illawarra bet sits inside that broader headwind, not apart from it. Any reader expecting this project to move on a timeline resembling the earlier, more fixed-bottom-friendly Gippsland prospect, which I covered in the feasibility grind at Star of the South, should recalibrate. Illawarra is harder water, a smaller zone, and a technology stack with less commercial runway behind it.
Why the grid would actually want this, eventually #
The case for persisting with Illawarra despite all that isn’t sentimental. Offshore wind blows more consistently at night and in winter than onshore wind in southern NSW, which is exactly the generation shape the NEM is short of as coal retires. NSW’s coal exit timeline, running through Eraring’s extended but still finite life and on to Liddell’s closure, is creating a reliability gap that onshore wind and solar alone don’t fully plug, a gap I’ve written about at length in the widening distance between NSW’s coal exit and its REZ rollout. Port Kembla also happens to be an existing heavy-industry load centre with deep water access and an underused industrial workforce that could plausibly pivot toward offshore wind assembly and maintenance work, which is the jobs argument the NSW government and BlueFloat both lean on in public statements.
I reckon that’s a legitimate long-run case. Whether it survives the next five years of floating wind cost reality is a separate question entirely, and I’m sceptical that the economics clear without either a much higher Certificate of Inclusion price under the federal CIS scheme or a direct government equity stake along something like the NSW government’s own offshore ambitions for the Hunter. The Clean Energy Regulator’s data on project financing patterns elsewhere in the NEM suggests floating offshore wind in Australia will need concessional capital it hasn’t yet secured here.
What would actually move this forward #
Three things would tell me this project has become real rather than aspirational. First, a granted feasibility licence with a defined project boundary and a public generation capacity range, not a zone-wide ceiling figure. Second, a connection agreement or at least a formal connection application lodged with Transgrid specifying a megawatt figure and a point of connection near Port Kembla. Third, a successful or attempted bid into a Commonwealth Capacity Investment Scheme offshore wind tender round, which would be the clearest signal yet that BlueFloat sees a bankable path rather than a holding position. None of those three things has happened as of now. AEMO’s Integrated System Plan continues to model offshore wind contributing to the NEM’s future capacity mix, but its own published work treats the actual delivery timeline for NSW projects as considerably more uncertain than onshore or battery builds, a gap I’ve set out before when comparing onshore and offshore wind through the connection queue lens.
The Illawarra zone deserves credit for being the more cautiously sized of NSW’s offshore prospects, shaped by genuine local negotiation rather than pure developer ambition. But cautious sizing doesn’t solve the floating turbine cost problem, and it doesn’t build the transmission corridor Port Kembla will need. I’ll keep checking the feasibility licence register and the Transgrid connection applications list every few months, because that’s where this project will actually show its hand, not in the next artist’s render of turbines dotting a horizon you’d need good eyes and a still day to see from Sandon Point anyway.
– Callum Hayes, Wind & Offshore Correspondent